Wiring Connections

9.0

W

IRING

C

ONNECTIONS

Refer to the drawings in this manual and any other drawings provided by Liebert for this installa-

tion. Make all of the following connections:

1. AC power cables from input power source circuit breaker (RIB) to UPS Module Input. Observe

phase rotation.

2. AC power cables from bypass power source circuit breaker (BIB) to UPS system bypass input at

System Control Cabinet (SCC). Observe phase rotation.

3. AC power cables from UPS Module Outputs to SCC or to switchgear for critical load bus.

Observe phase rotation.

4. Each UPS Module Output Neutral to SCC or to switchgear for critical load bus. See Section 7.

!

DANGER

VERIFY THAT ALL INCOMING HIGH AND LOW VOLTAGE

POWER CIRCUITS ARE DE-ENERGIZED AND LOCKED OUT

BEFORE INSTALLING CABLES OR MAKING ELECTRICAL

CONNECTIONS.

ALL POWER CONNECTIONS MUST BE COMPLETED BY A

LICENSED ELECTRICIAN EXPERIENCED IN WIRING UPS

EQUIPMENT, AND IN ACCORDANCE WITH ALL APPLICABLE

NATIONAL AND LOCAL ELECTRICAL CODES.

IMPROPER WIRING MAY CAUSE DAMAGE TO THE UPS OR

INJURY TO PERSONNEL.

!

CAUTION

All shielded cables, non-shielded cables, non-shielded control

wires, non-shielded battery breaker control wires, and non-

shielded remote control wires must be housed in individual,

separate, steel conduits. Placing multiple cables in the same

conduit with other control or power wiring may cause system

failure.

!

CAUTION

See Section 7 of this Manual for an explanation of proper

grounding techniques.

NOTE

Make sure all required wiring between each UPS module and the optional

cabinet(s) is completed. Observe phase rotation.