INSTALLATION

EATON Powerware

®

9125 Two-in-One UPS (2500/3000 VA) User’s Guide

S 164201374 Rev D

www.powerware.com

21

NOTE Pedestals are required for installations with one or two cabinets. Joining brackets
are required for installations with two or more cabinets.

Air Vents

Figure 12. Tower Setup with Three Cabinets

10. Align each joining bracket with the adjacent corner screw holes and

secure with the supplied screws (see Figure 13).

Joining Bracket

EBM

UPS

Joining Bracket

Figure 13. Installing the Joining Brackets (Top View with Pedestals)

11. If installing additional EBMs, repeat Step 10 for each cabinet.

12. If installing optional EBMs, continue to the following section,

“Extended Battery Module Installation.” Otherwise, continue to
“Plug-Receptacle UPS Installation” on page 25 or “Hardwired UPS
Installation” on page 27 to complete the installation.