Connect steam boiler piping

General steam piping information:

Hartford loop piping arrangement and wet return are required for

1.

steam boilers. Use the Hartford loop for both pumped-return and
gravity-return systems.

Maintain 24-inch minimum from waterline to bottom of header (63"

2.

from bottom of section).

When using condensate receiver, feed pump must be energized by

3.

boiler-mounted pump controller.

Install piping:

4.

Install piping as shown on

a.

page 17 through page 18 for single boil-

ers. See page 19 for additional requirements when piping multiple
boilers.
Return pipe sizing.

b.

Pumped return — Size return piping by pump.

s

Gravity return — Size gravity return same as Hartford loop

s

equalizer pipe size.

Drain valve — Install system drain valve in lowest part of return

c.

piping close to boiler. See Figure 17, page 15, for sizing.
Cold water fill piping — Connect cold water fill piping as shown in

d.

Figure 20. Also shown are recommended valves and water meter,
if used. Water meter will detect added makeup water, indicating
leaks in system.
Condensate return piping:

e.

Satisfactory operation of any steam heating system depends on

s

adequate return of condensate to maintain steady water level.

Avoid adding excessive amounts of raw make-up water.

s

Where condensate return is not adequate, a low water cutoff

s

with pump control, condensate receiver, and condensate boiler
feed pump should be installed.

See

s

Figure 21 for piping and Figure 22 for sizing.

Cold water fill piping

&IGURE

Condensate piping to boiler

&IGURE

Condensate receiver capacity required

&IGURE

Boiler

model number

I=B=R gross output

(lbs steam per hour)

Gallons condensate

per hour

Minimum condensate receiver capacity (gallons) (Note 1)

Recommended condensate

feed pump capacity

GPM at 15 PSI

15-minute boiler

operation

30-minute boiler

operation

45-minute boiler

operation

60-minute boiler

operation

488

810

97

29

58

87

116

3.2

488R

794

95

28

57

85

114

3.1

588

1084

130

39

78

117

156

4.3

688

1358

163

49

98

147

196

5.4

788

1632

195

59

117

176

234

6.5

888

1904

228

68

137

205

273

7.6

988

2170

261

78

157

235

313

8.7

988R

1991

239

72

145

217

289

8.0

1088

2452

294

88

176

265

353

9.8

1088R

2304

277

83

166

249

332

9.2

1188

2724

327

98

196

294

392

10.9

1288

3000

360

108

216

324

432

12.0

1388

3270

392

117

235

353

470

13.1

1488

3550

426

127

255

383

511

14.2

1588

3820

458

137

274

412

550

15.3

1688

4090

490

147

294

441

588

16.4

1688R

3980

478

143

287

430

574

15.9

1788

4370

524

157

314

471

629

14.5

1888

4640

557

167

334

501

668

18.6

Note 1 — Maximum time to when condensate returns to boiler — the longer the time for condensate to return, the larger the receiver must be.