6 Setup

VEGASWING 66 • - two-wire

44952-EN-130805

High coverage (detected errors)

This test is valid if you cannot change the vessel filling or cannot

dismount the sensor.
This function test can be carried out with measurement setups in

conjunction with the two-wire electronics module.
The recurring function test according to IEC 61508 can be carried

out through a short interruption (> 2 seconds) of the supply line to the

sensor. This starts a test sequence.
By doing so, a test procedure is started. The correctness of the sub-

sequent switching conditions on the indications of the SPLC must be

monitored.
a. Short interruption of the supply line to the sensor

You can carry out the function test with the outputted current values

also directly via a safety PLC or a process control system.
1. Separate the instrument briefly (>2 s) from voltage supply.

Check if all three switching conditions change in the correct

sequence and the specified duration. By doing so, you can check

the function of the measuring system.
You can find the test procedure under "Implementation - Function

test".
Make sure the connected downstream devices are activated dur-

ing the function test.

2. Set the mode switch (min./max.)

Check if the switching status changes (signal lamp - switching

status). By doing so, you can check the function of the measuring

system.
If this is not the case, then there is a fault in the measuring sys-

tem.
Make sure the connected downstream devices are activated dur-

ing the function test.

b. Pushing the test key

An integrated test key is lowered in the front plate of the signal con-

ditioning instrument of in the electronics module of the VEGASWING

66. Push the test key for > 2 seconds with a suitable object.
1. Push the test key.

Check if all three switching conditions change in the correct

sequence and the specified duration. By doing so, you can check

the function of the measuring system.
You can find the test procedure under "Implementation - Function

test".
Make sure the connected downstream devices are activated dur-

ing the function test.

2. Set the mode switch (min./max.)

1 Short interruption of the

supply line to the sensor