Distributor Pipe Control - Farm/Commercial

1. Bolt stub shaft (DPC0003) to the index tube assembly, aligning notch in flange with sheave and using

three (3) 5/16" x 1" HHCS bolts (S-1196) and three (3) 5/16" flange nuts (S-3611).

2. Using the 5/16" x 1-3/4" roll pins (S-8397), connect the 5" pipe coupler (DPC0012) to the stub shaft.

3. Install cable (not included) to connect the distributor index assembly to the control lever. Secure the

cable to the distributor index assembly as shown using a cable clamp. Run the cable down the center
of each piece of pipe as they are attached.

(See Figure 2.)

Figure 2 Stub Shaft and Cable

Cable clamp

Cable (not
supplied)

Install cable as pipe is installed.
It runs down center of pipe.

Pipe control stub
shaft (DPC0003)

5" Pipe coupler (DPC0012)

5/16" x 1-3/4"
Spring pin (S-8397)

5/16" x 1-3/4"
Spring pin (S-8397)

20' Long control pipe (DPC0001)

5/16"-18 x 1" Bolts (S-1196)
and 5/16" flange nuts (S-3611)