Evolution Series E9000 Installation & Maintenance Guide

Figure 32. Rotating the operating handle to access the breaker.

Pilot Bracket and Door

The pilot device door can be removed by lifting straight
off per Figure 33. Also, the metal bracket can be removed
by loosening mounting screws and removing bracket.

Figure 33. Grasp the center of the door.

Figure 34. Pilot Device Bracket locking bracket in door

The pilot device bracket in is locked in place using the
door mounted locking bracket shown in Figure 34.

NEMA 3R Outdoor Enclosure Installation

NEMA 3R Installation Instructions

1. Remove left rear cover on right shipping module (Figure 1.) Save

the screws for later reassembly of the cover. Note that the left
module right rear cover has a flange that will be underneath
the removed covered with it is replaced. This provides an over-
lapping connection in the rear of the two spliced modules
(Detail C).

2. Slide adjoining shipping modules as close together as possible

while carefully aligning the modules front-to-back.

3. Join shipping modules together using (4 sets) 1/2 hardware

(front only). Hardware kits shipping with modules.

4. Assemble bus splices per splice instructions (included in splice

kit).

5. Install wireway transition channel barrier by sliding it though

the 5 x 5 wireway cutout and attaching it using (1) 1/4-28 x 3/8
thread rolling (Figure 3).

6. Re-attach right, rear cover by re-attaching 1/4-20 x 5/8 sealing

screw (Detail C).

7. Attached center cap using (8) 1/4-20 x 5/8 thread rolling screws

(Figure 1).

Notes:
1. 3-inch floor members can be installed similarly to standard

MCC flor members.

2. Module doors can be removed by removing 1/4-20 x 3/8 thread

rolling screws from door hinge bracket (Detail D).