INSTALLATION

Prepare Pit

Before lowering the dock leveler into the pit, the

following must be performed:

1. Remove all debris from the pit and sweep the pit

clean.

2. Check the entire dock leveler pit for proper

construction according to approved/certified pit

drawings. Make sure pit is square by making the

following measurements:

• Measure pit width distance (A) at both front and

rear of pit.

• Measure dock floor-to-pit floor distance (B) at all

four corners.

• Measure pit length distance (C) at both sides.

• Measure corner-to-corner (criss cross) distance

(D) at both sides. Take measurements at dock

floor level and at pit floor level.

If any measurement is off by more than 1/8 in.

(3.18 mm), contact Poweramp

®

Technical Services

before proceeding.

3. Make sure the field junction box for the dock leveler

(E) is at the correct location per pit diagrams.

A—Distance (Pit Width)

(Front and Rear)

B— Distance (Dock Floor-to-Pit

Floor) (All Four Corners)

C— Distance (Pit Length)

(Both Sides of Pit)

D— Distance (Pit Corner-to-Corner) (Top,

Bottom, and Both Sides)

IMPORTANT

DO NOT remove the shipping bands around the

dock leveler lip until instructed to do so.

Post safety warnings and barricade the work area at

dock level and ground level to prevent unauthorized

use of the dock leveler before installation has been

completed.

Failure to follow the installation instructions can

result in damage to dock leveler, the facilities, and/

or serious personal injury or death.

Only trained installation professionals with the

proper equipment should install this product.