ARC Top Load Rebuild Procedure

Using a small standard screwdriver remove snap
ring. See Figure 52.

Figure 47

Remove spring plate, upper spring cover(if
applicable), spring, and lower spring cover (if
applicable) from top-load assembly. See Figure
53.

Figure 48

Remove internal shaft and inspect for wear,
replace as necessary. Clean all parts. See Figure
54.

Figure 49

Install new pins, apply a thin layer of grease to
internal shaft and pins. See Figure 55.

Figure 50

Remove seal and replace. See Figure 56.

Figure 51

Apply a thin layer of grease the seal and bore. See
Figure 57.

Figure 52