1. Scope

This inspection standard applies to the DC402G Converter for Conductivity or Resistivity.

2.

Inspection Items
2.1 Insulation resistance test

* 2.2 Dielectric strength test

2.3 Current output test

2.4 Contact operation test

2.5 Temperature indication check

2.6 Resistance indication check
Note: Items marked with an asterisk (*) may only be confirmed by a test certificate.

3.

Inspection Methods, Standards and Conditions

Connect the testing circuit as shown in Figure 1. Allow the instrument to warm up for

at least 5 minutes before conducting the tests. For the connections for the insulation

resistance test, follow the instructions in Sections 3.1.

Performance tests should be done in the inspection mode where the tests from

Section 3.3 through Section 3.6 take place in sequence and cannot be retraced. If the

reconfirmation of a test is needed, turn off the power to the converter, turn on the

power again, and enter the inspection mode to restart the tests.

3.1 Insulation Resistance Test

Apply 500 V DC between the power supply terminals shorted together (1 and 2) and the

protective earth terminal outside the case. The insulation resistance must be 100 MΩ or

greater.

3.2 Dielectric Strength Test

Apply 1400 V AC, an AC voltage of substantially sinusoidal waveform with a frequency of

50 Hz or 60 Hz, between the power supply terminals shorted together (1 and 2) and the

protective earth terminal outside the case, for at least 2 seconds. The insulation must

withstand this voltage. (The sensed current should be 15 mA.)

3.3 Current Output Test

Connect the testing circuit as shown Figure 1 and set the equipment as follows:

Decade resistance box 1 (temperature simulation input):

960.9 [Ω]

Decade resistance box 2 (conductivity simulation input):

160 [Ω]

The power supply voltage should be set in accordance with the specifications of the

converter.

User the following procedure to enter the inspection mode.

(1) Entering Service Code 87.

a. Press the [] key. The message display will show “SETP.”

b. Press the [NO] key until the message display shows “SERV.”

c. Press the [YES] key. The data display will show “00” with the first digit of 0

flashing.

d. Press the [] key eight times. The data display will show “80” with the first digit of

8 flashing.