6.3 Preparations For Installation

Installation should comply with NFPA 72E, as applicable to flame detectors.
The detectors can be installed with the use of general-purpose common tools
and equipment.

1 Verify the appropriate Purchase Order. Record the part number and Serial

number of the detectors and the installation date in the appropriate Log-
book.

2 Open the container package prior to detector installation and visually inspect

the detector.

3 Verify that all components required for the detector installation are readily

available before commencing the installation. In case that the installation is
not completed in a single session, secure and seal detectors and conduits.

4 For wiring, use color coded conductors or suitable wire markings or labels.

Wire diameter between 12 to 20 AWG (3.1 x to 0.5 mm

2

) may be used for

site wiring. The selection of wire gauge should be based on the number of
detectors used on the same line and the distance from the control unit, in
compliance with specifications (see Appendix A)

6.4 Conduit Installation


1 To avoid water condensation in the detector, it should be installed with the

conduits placed downward, and should include drain holes.

2 When using the optional swivel mount, use flexible conduits for the last

portion connecting to the detector.

3 For installations in atmospheres as defined in Group B of the NFPA, conduit

inlets should be sealed.

4 When pulling the cables through the conduits, ensure that they are not

tangled or stressed. Extend the cables about 12 in. (30 cm) beyond the
detector location to accommodate wiring after installation.

5 After the conductor cables have been pulled through the conduits, perform a

continuity test.