Installation & Maintenance : 6259675 IM V1.4.0 10/2013

Commissioning Procedure

CAUTION

Disable remote ON/OFF to ensure the unit does not start unintentionally.

The unit will not start until microprocessor control SWITCH 1 is in the ON position.
DO NOT SWITCH TO ON AT THIS STAGE

Adjust the temperature supply and return set points (if necessary, via the chosen
control management scheme) to call for 100% cooling (refer to the

Controls

section).

Ensure all KNOBS and SWITCHES are adjusted to suit the design requirements
(refer to the

Controls

section).

To switch the unit ON, use the microprocessor keypad as follows:

Press

Prg

, press

, press

, press

& finally

.

CAUTION

There will always be a delay between the enabling of the unit and the energising of
the compressor contactors, anything between 1 to 2 minutes. Be patient.

Check that each circuit trips on low pressure. The alarm should appear within
3 minutes.

The alarm will be recognised at the display circuit trip, to clear the alarms refer
to

Alarm Handling

.

To switch the unit OFF, use the microprocessor keypad as follows:

Press

Prg

, press

, press

, press

& finally

.

Fully open all liquid line and discharge service ball valves on each circuit.