Commissioning Procedure

COMMISSIONING
CHECKLIST

The following should be carried out with a load on the system, otherwise the unit is likely
to short cycle. The following tests are to be carried out on 1 circuit at a time.

Switch the door interlocking MCCB to the ON position but again only on the circuit
which is to be tested.

Adjust the temperature supply and return set points to match the
system requirements.

To switch the unit ON, use the microprocessor keypad as follows:

Press

Prg

, press

, press

, press

& finally

.

Check pressures at suction and discharge ports for correct phase rotation.

CAUTION

If no differential pressure occurs, isolate immediately.

RECORD

Measure and record the compressor amps once the compressors are fully loaded
and at the unloading stage.

Measure and record full speed amps of each condenser.

CAUTION

The microprocessor LP setting is adjustable via the microprocessor keypad,
factory set to 3.2BarG.

RECORD

Check the liquid line sight glass is clear and dry.

Check the superheat setting adjusts the expansion valve to maintain a superheat
setting of 5 – 8°C at all operating loads.

Check and record the following:

Suction and discharge pressures

Liquid, discharge and suction line temperature

Ensure the above are all within the design parameters.

Repeat as follows for each circuit:

To switch the unit OFF, use the microprocessor keypad as follows:

Press

Prg

, press

, press

, press

& finally

.

To switch the unit ON, repeat above.

The unit is now commissioned and will provide many years of trouble free operation
providing the following maintenance schedule is followed.