Table 34 Test results (continued)

Explanation

Test Results

This portion of the test was skipped. Either a scratch tape was not
present or the library was not configured for the test.

SKIPPED

A warning is additional information about the test. For example, if
a calibration failed, but the stored offsets are analyzed, a warning
states that the offset check might not be accurate.

WARNING

The test was interrupted. The log provides a record of the test
interruption.

STOPPED

Verification test graphical reports

Some verification tests produce graphical reports that let you easily see if the test generated PASSED,
MARGINAL, or FAILED results. Each result is shown in a different color:

P = passed (green)

M = marginal (yellow)

F = failed (red)

There are eight types of graphical reports. Each individual test generates two or more graphical
reports (except for the scan barcode test, which does not generate graphical reports). The following
sections show an example of each type of graphical report and actions to take to correct a marginal
or failed result.

To view the graphical reports for a test, click Reports on the Verification Tests window.

Joint alignments

The joint alignment graphical report shows the results for tests of alignment between frames and
tests of accessor travel to all corners of the library.

If the graphical report shows one or more failed results for joint alignment, realign the middle
X-axis rail and check the alignment of the top and bottom X-axis rails at the location of the
failure.

If all the joints passed testing but accessor movement failed, manually move the accessor down
the aisle in each direction to locate any places where motion of the accessor is not smooth or
is restricted. Then realign the middle X-axis rail and check the alignment of the top and bottom
X-axis rails at the location of the failure.

Vertical alignments

The vertical alignments graphical report shows the results for test of vertical alignment of tape
magazines on the drive-side and door-side of each frame, and for vertical alignment of each I/E
station.

If the graphical report shows a failed result for the drive-side or door-side, ensure that all tape
magazines are installed properly on that side and that the calibration targets are correctly
snapped on to the magazines.

If the graphical report shows a failed result for the I/E station, ensure that the I/E station and
front door are completely shut.

If running the test again still generates failed results, realign the middle X-axis rail and check
the alignment of the top and bottom X-axis rails at the location of the failure.