18

Chapter 3: Installing the Gateway in the Enclosure

6. Trim the wire tie and seal the grommet with tape and silicone sealant.

Caution

The grommet must be sealed so that the unit can operate correctly in an outside environment.

Prepare for Initial Startup

To complete the installation, perform the following procedure:

1. Install an uninterruptible power supply according to the manufacturer’s instructions.

2. If necessary, plug the management cable into the console port. For networks with remote management

enabled, no local configuration is required.

3. The physical installation is now complete, as shown in Figure 12.

Figure 12. Configuration Complete