Vertical contact toaster, Maintenance (continued) – A.J. Antunes & Co VCT-2000 9210212 User Manual

Page 14

Advertising
background image

VERTICAL CONTACT TOASTER

14

P/N 1010875 Rev. C 02/13

Figure 12. Removing Conveyor Belt Chains

Figure 11. Removing Conveyor Belt Chains

Rotation

Upper Support Rod

Large Link

(P/N 0800121)

Small Link

(P/N 0800204)

Conveyor Belt Chains (Every 3 to 6 months)

MEASURING CONVEYOR BELTS CHAINS

1. Set the compression knobs to 6 and F.
2. Open the Front Conveyor Cover and locate the

approximate center point of the Conveyor Chain.

3. Pull the Conveyor Belt Chain away from the edge

of the toaster.

4. Stand a U.S. Dime 11/16” (18 mm) coin on end

between the frame and the chain (Figure 11).

5. If the gap is significantly than the coin, adjust the

Conveyor Belt Chain as described below.

6. Use the same steps to check the rear Conveyor

Chain.

ADJUSTING CONVEYOR BELT CHAINS

After a time, the Conveyor Chain links will wear and

the Conveyor Belt chain will stretch, eventually skipping

on the sprockets. This is easily remedied by removing

one or more conveyor links from each side of the belt.

There are two 1/2” small links

on each side of the con-

veyor belt. The others are large, 3/4” long (Figure 12).
1. Turn the Rocker Switch off, unplug the power

cord, and allow the unit to cool.

2. Remove the Bun Feeder and Heat Shield and set

the Compression Control Knobs to 6 and F.

3. Open both Conveyor Covers and pull the Belt

Wrap Pin out of the “zipper” (Figure 8).

4. Remove and the Belt Wrap(s).
5. Disconnect the Conveyor Belt Chain by squeez-

ing any two links together and unhooking both

ends of one link (Figure 12).

3. To shorten a stretched Conveyor Belt Chain,

remove one 1/2” link from the belt.

4. Reassemble the Conveyor Belt Chain onto the

sprockets as described below.

NOTE: If the belt is too short to be reassembled,

remove an additional 1/2” small link and install a

3/4” large link. This will shorten the belt 1/4” over-

all.

REPLACING CONVEYOR BELT CHAINS

1. Turn the Rocker Switch off, unplug the power

cord, and allow the unit to cool.

2. Remove the Bun Feeder and Heat Shield and set

the Compression Control Knobs to 6 and F.

3. Open both Conveyor Covers and pull the Belt

Wrap Pin out of the “zipper” (Figure 8).

4. Remove and the Belt Wrap(s).
5. Disconnect the Conveyor Belt Chain by squeez-

ing any two links together and unhooking both

ends of one link (Figure 12).

6. Remove the Conveyor Belt Chain.
7. Place the new Conveyor Belt Chain on the top

sprockets with hook ends down. Check for correct

positioning (Figure 12).

NOTE: The ends of the hooks must point down.

(Figure 12).
8. Wrap the Conveyor Belt Chain around lower

sprockets and connect by hooking both ends

together.

NOTE: Make sure the Conveyor Belt Chain is

installed under the upper Support Rod and over the

lower Support Rod.

WARNING

Turn the power off, unplug the power cord and

allow the unit to cool down before performing any

service or maintenance.

MAINTENANCE (continued)