EXTENDED ROOF BRACKET

INSTALLATION

If the chimney extends more than 4 feet above

the roofline, an Extended Roof Bracket must

be installed at every 4-foot increment of height

above the roofline, leaving no more than 4 feet

extending above the last pipe band.

1. Mount Pipe Band: Slip the Pipe Band

around the chimney and secure by tightening

the nut and bolt.

2. Install Roof Brackets: Measure from the

Pipe Band to the points where the conduit will

meet the roof, and form approximately a 60°

angle with the chimney, and with each other.

(Figures 18 and 19). Cut 2 pieces of 3/4 inch

thin wall galvanized steel electrical conduit,

(or rigid galvanized tubing) to these lengths.

The conduit is not furnished by DuraVent,

and must be locally procured. Mount the two

Roof Brackets where the conduit meets the

roof, using 6 roofing nails per bracket. Seal

the nail heads carefully with a non-hardening,

waterproof sealant.

3. Attach Conduit: Flatten 1 inch and drill

a 1/4-inch hole at each end of both pieces of

conduit. Bolt each conduit to the Pipe Band

and Roof Brackets with the nuts and bolts

provided.

Figure 20

A MINIMUM OF 2 INCHES

BELOW FINISHED CEILING

18 INCHES MINIMUM FOR

SINGLE-WALL STOVEPIPE

CAP

SDP-C

STORM COLLAR

SDP-SC

VENTILATED FLASHING

SDP-F

CHIMNEY SECTIONS

SDP-P

ROOF

FRAMED OPENING

SqUARE CEILING SUPPORT

BOx SDP-SB

PUSH SUPPORT BOx UP

THROUGH ROOF, TRIM

AND FOLD BACK ExCESS

AS SHOWN IN FIG. 22

Figure 18

ExTENDED

ROOF

BRACKET

SDP-RSA

CHIMNEY SECTION

SDP-P

3/4 INCH THIN-WALL

GALVANIZED ELECTRICAL

CONDUIT (NOT FURNISHED)

60º

Figure 19

CHIMNEY CAP SDP-C

ExTENDED ROOF BRACKET SDP-RSA

STORM COLLAR SDP-SC

FLASHING SDP-F,

SDP-TF

60º

CONSISTS OF: (1) PIPE BAND, (2) ROOF BRACKET CONNECTED

WITH 3/4 INCH THIN-WALL GALVANIZED ELECTRICAL CONDUIT. (NOT

FURNISHED BY SIMPSON DURA-VENT). FLATTEN ENDS AND BOLT TO

PIPE BAND AND BRACKET.

NOTE: IF

DIMENSION ‘A’

IS GREATER

THAN 4-FEET,

ExTENDED

FOOF BRACKET

MUST BE USED.

A