4.2 C

ABLE INSTALLATION

The power supply connectors and interfaces of this device are installed inside the case.

Cables can be routed through rubber grommets and exit the case on the bottom. The

grommets are inserted between the case and the cover, and can easily be removed after

removing the cover. Since this device includes the required input peripherals (soft

keyboard / touch screen), only one grommet for the power supply cable (cable diameter of
6...7mm) as well as three blank plugs are integrated by default. Should it be required to

feed through more cables from the device to the outside, these blank plugs must be

replaced by suitable grommets (optionally available accessories).

Pos: 18 /Datentechnik/Inbetriebnahme/Reihenfolge der Inbetriebnahme/Reihenfolge der Inbetriebnahme für VMT 50xx-Serie @ 0\mod_1158848845491_681.doc @ 803 @

4.3 O

RDER OF COMMISSIONING STEPS

Remove the case cover screws and carefully remove the cover.

Fix the wires of the power supply cable in the screw terminals by using Phoenix

Combicon in wire end sleeves.

Plug the data cable connector on the desired interface connector and screw it on,

if possible.

Select a cable grommet with a suitable diameter for each cable to be fed through,

and enclose the cable with it. Additionally there are cord grips for different cable

sizes available.

Remove the blank plug and replace it with the grommet surrounding the cable.

Attach the case cover properly and install the screws.

Note:
The service slot is fixed with captive screws.

Warning:
Full protection according to the indicated protection class is only ensured if the case cover

is properly installed!

Pos: 19 /Datentechnik/Inbetriebnahme/Betriebsbereitschaft prüfen/Betriebsbereitschaft prüfen für OPC/CPC/PLC/OTC/ITC/VMT-Serie(+Monitore) / IPC 5100/5500/2400/1100 @ 0\mod_1158905578361_681.doc @ 806 @

4.4 C

HECK OF READINESS FOR OPERATION

Check the device for any hidden damage caused by improper transport, improper

operating or storage conditions or by improper use (e.g. smoke development from the

device, etc.). Immediately shut down the device and prevent any further accidental

commissioning if any damage is detected.

Advertising