10

3.0 Installation

3.1 Unpacking the HS-3100 or HS-3200

The basic HS-3100/HS-3200 package includes the following components:

Backbox

Outer door including:

Lock

Display window

Inner dead-front door including:

Display PCB

Operating instruction insert

Hotkey label insert

Wiring label

Hardware backplate including:

Main PCB

Transformer

Ribbon Cable for expansion modules

Plastic Shield

Hardware pack including:

2 x NAC EOL resistors

Door keys (taped to outside of cabinet)

Installation manual and operating manual

3.2 Mounting and Assembling the HS-3100/HS-3200

Note: All applicable codes and standards should be considered. Specific reference should be
made to NFPA 72, or ULC-S524 and CEC Part 1 Section 32.

Surface and Flush Mounting

The HS-3100/3200 can be mounted in either flush or surface mount installations. Before installing
the HS-3100/3200 Panel the following should be considered.

1.

Determine a suitable location for mounting the FACP. Keep in mind that surrounding
walls, fixtures, must not hinder access to internal components. etc.

2.

Determine the size and location of conduit entrances. The Backbox provides various
knockout locations, however should it be necessary to cut additional conduit entrances the
electronics must be removed to avoid metal chip contamination. Reference the ’Remove
Electronics’ paragraph on the following page.

Note: Removing the inner door, outer door, and plate-mounted electronics is recommended in all
HS-3100/3200 installations.

3.

The enclosure must be mounted to provide a 135

o

(minimum) angle of rotation of the outer

door to insure easy removal or assembly.

4.

Mark placement of mounting hardware, drill holes and install plugs (if necessary).

5.

Secure the FACP to the wall using hardware suitable to the wall construction. Support
backbox in place while inserting hardware and ensure that the backbox is level and plumb
before tightening.

Note: Please see the detailed diagram (Figure 1) for location of knockout and mounting holes.