9 testing – Trebor 110E User Manual

Page 20

Advertising
background image

PAGE 20

MODEL 110E PUMP OPERATION / MAINTENANCE MANUAL

4.9 TESTING

4.9.a Performance Test

Start with air regulator at low (< 15 psi) pressure setting.

Pump must prime once pressure is increased

60 psig Supply Pressure

Check for fluid leaks, listen for air leaks, check for irregularity

Prepare the pump for drying

4.9.b Dry Pump

Connect vacuum hose to discharge line

Connect purge line to fluid inlet

60 psig Supply Pressure

Cycle pump & vacuum dry by rotating pump side to side for 30 seconds.

Turn off Air Supply and allow the pump to purge for 5 minutes.

4.9.c Dry Suction

20 psig Supply Pressure Target

Record Suction Value

Target = 6in-Hg.