SSG BRIDGE INSTALLATION

RUN SEALANT ACROSS

FACE OF MULL AND TOP

OF HORIZONTALS

HP175-FP-61

BRIDGE

1) BED FACE OF MULL

AND TOP OF HORIZONTALS

WITH SEALANT.

2) SET HP175-FP-61 BRIDGE

INTO PLACE. HOOK OVER DRIP

LEGS AND ROTATE INTO

PROPER POSITION.

3) SEAL AND TOOL ACROSS

FACE OF MULL AND HORIZONTALS

4) SEAL CLIP POCKET AT EACH END OF BRIDGE

5) SEAL ABOVE AND BELOW DRIP LEG OF

HORIZONTALS

SEAL ACROSS FACE

OF BRIDGE AT

DRIP LEG

SEAL CLIP

POCKET AT EACH

END OF BRIDGE

STEP 1

STEP 2

GLAZE SYSTEM FROM BOTTOM TO TOP.

INSTALLING DIVERTERS TO HORIZONTAL

ABOVE AS YOU PROCEED UP BUILDING.