4 Installation

4.1

Before the Mounting

The foundation for the mounting kit must be horizontal (use spirit level), flat and rigid for the loads to

be supported.
The load must be distributed as symmetrical as possible in order not to partially overload the load cells.

The foundations of the mounting kits must be aligned and the supporting surfaces of the weighing
object (e.g. vessel) must mount in parallel.
If soft layers (e.g. from rubber or plastic) for vibration damping or for temperature insulation are

inserted between mounting kit and vessel and / or between mounting kit and supporting construction,

you must take care to insert between soft layer and mounting kit a load equalisation plate to ensure an
even load distribution on the mounting kit.
The version of insulation and equalization plates is application-dependent.

4.2

Tightening Torques

Insert a washer between bolt head and mounting kit. Suitable bolts and washers as well as the

recommended tightening torque are given in the table below.

Mounting kit

Bolt
DIN 4014 or DIN 4017

Washer
DIN 7349

Tightening torque

PR 6002/02S
PR 6002/03S
PR 6002/04S
PR 6002/05S
PR 6002/10S
PR 6002/11S
PR 6002/20S
PR 6002/21S

M12-A2-70 13Ч30Ч6 A2

70 Nm