Installation

Technical Information for the Installer

In order to install the hob into the kitchen fixture, a hole with the dimensions shown in fig. 12 has to be
made, bearing in mind the following:
– within the unit, between the bottom of the hob and the upper surface of a shelf there must be a

clearance of at least 30 mm.

– It is absolutely essential that you place a separator between the base of the hob and the built-in unit or

the oven.

– the hob must be kept no less than 200 mm away from any side wall (fig. 12).
– the hob must be installed at least 60 mm from the wall.
– there must be a distance of at least 650 mm between the hob and any wall cupboard or extractor hood

positioned immediately above (see fig. 14).

– if the hob is installed over a built-in

oven, there must be a distance of
at least 30 mm between the two
appliances. The two appliances
should be connected to the
gas supply with independent
connections

200 mm min

500 mm

450 mm

650 mm

60 mm min

860

480

500

60 min

0

– 2

840

200

min

0

– 2

Installation in Kitchen Cabinet with Door

It is recommended that a 30 mm clearance be left
between the cooktop and the fixture surface (fig. 13).

30 mm

Space for

connections