LOCATING THE BOILER

Minimum Clearance Dimensions

Table 2 - Minimum Clearances

Alcove

Top

6”

(152mm)

Rear

6”

(152mm)

Control Side

7”

(178mm)

Opposite Side

6”

(152mm)

Front

18”

(457mm)

Flue/Vent Connector

6”

(152mm)

Near Boiler Piping

2”

(51mm)

WARNING

Improper installation, adjustment, alteration, service

or maintenance could result in death or serious

injury

.

!

1.

Installation must conform to requirements of authority

having jurisdiction or, in absence of such requirements,

to the National Fuel Gas Code, ANSI Z223.1/NFPA 54.

2.

Where required by authority having jurisdiction,

installation must conform to the Standard for Controls

and Safety Devices for Automatically fi red Boilers,

ANSI/ASME CSD-1.

3.

Boiler series is classifi ed as Category I. Vent

installation shall be in accordance with "Venting of

Equipment ," of the National Fuel Gas Code, ANSI

Z223.1/NFPA 54, or applicable provisions of local

building codes.

4.

Boiler installed in building under construction; take

care to insure clean combustion air supply during

construction process. Airborne particulates from drywall

dust and fi berglass insulation can clog burner ports and

cause incomplete combustion and sooting.

5.

Boiler shall be installed such that gas ignition system

components are protected from water (dripping,

spraying, rain, etc.) during appliance operation and

service, (circulator replacement, condensate trap,

control replacement, etc.).

6.

Locate boiler on level, solid base as near chimney as

possible and centrally located with respect to heat

distribution system as practical.

7.

When installed in utility room, door should be wide

enough to allow largest boiler part to enter, or to

permit replacement of another appliance such as water

heater.

8.

Accessibility clearances take precedence over fi re

protection clearances. An 18-inch clearance should be

maintained on any side where passage is required to

access another side for cleaning, servicing, inspection

or replacement of any part that may need attention. An

18-inch clearance is recommended on the control side

for servicing.

9.

Locate equipment which allows the facilities for

ventilation satisfactory combustion of gas, proper

venting, and maintenance of ambient temperature at

safe limits under normal conditions of use. Equipment

shall be located so as not to interfere with proper

circulation of air. When normal infi ltration does

not provide the necessary air, outside air shall be

introduced (See “Fresh Air for Combustion”).

10.

Keep air passages free of obstructions. Ventilation

and combustion air must enter boiler room without

restrictions.

WARNING

Fire hazard. Do not install boiler on combustible

fl ooring or carpeting. Failure to follow these

instructions could result in death or serious injury.

!

11.

FOR INSTALLATION ON NON-COMBUSTIBLE

FLOORS ONLY - For installation on combustible

fl ooring special base must be used. (See Replacement

Parts Section.) Do Not install Boiler on carpeting.

NOTE: Greater clearances for access should supersede fire

protection clearances.

* Defi nition of Alcove is three sided space with no wall in

front of boiler. ANSI standard for alcove is 18 inches from

front of appliance to leading edge of side walls as shown

below.

Minimum Clearances to Combustible

Construction (as seen from above)

7"

6"

BOILER

18"

6"

Front

Control

Side