Current transformer (ct) connection, Section, Current transformer (ct) – CIRCUTOR OPTIM-EMS-C Series User Manual

Page 15: Connection

Advertising
background image

3.9.- CURRENT TRANSFORMER (CT) CONNECTION

A current transformer (CT) outside the capacitor bank must be installed to

measure the total load current, plus that of the capacitor bank itself

(

Figure 8

).

The standard transformer must have a nominal output of 5 A at the secondary.

We recommend connecting the CT to phase L1 in the direction of the current flow

from P1 to P2 (

Figure 8

) and connecting the secondary (terminals S1, S2) to the

capacitor bank terminals with the same name (

Figure 8

).

Avoid the flow of current through the CT's primary before connecting the second-

ary to the S1 and S2 terminals of the capacitor bank.

If the CT must be installed while the installation is under load, short-circuit S1 and

S2 while they are not connected to the capacitor bank.

The current value of the CT primary winding must be equal to or slightly greater than the size of

the mains switch of the installation. Therefore, the CT must be able to measure the maximum

current expected to be consumed by all the loads being compensated.

Figure 8: Installation of the external current transformer (CT).

The connection point of the CT for a capacitor bank that compensates an entire installation is

after the mains switch of the installation.

To prevent excessive attenuation of the signal, it is recommended that the minimum cross-sec-

tion of the secondary winding cable (terminals S1, S2) is at least

2.5 mm

2

.

15

Instruction Manual

OPTIM EMS-C series

Advertising