installing power supply for other emerald ops

WARNING

NOTE: DO NOT PLUG IN UNTIL SYSTEM IS COMPLETELY WIRED AND CHECKED FOR

POLARITY. Irreversible system damage will result if polarity is not kept.

INSTALL THE POWER SUPPLY

Mount the power supply unit to the wall in a secure location as close to each Emerald OP as

possible. Use angle brackets and screws for mounting. Exception: 1st power supply in Lencore

branded enclosure for SmartSwitch and 1st Emerald OP.

Keep top fan and side vents exposed!

Take note of the three (3) positive and three (3) negative power terminals.

Do not plug in until system is completely wired and checked for polarity.