3. LIFT SUPPORTING STRUCTURE:

The Plasma Two Lift can be
mounted from four 1/2" threaded
rods spaced at 34.75" Wide
(88.26 cm) x 12.25" Deep (31.11
cm)
-as shown in figure 3. The
threaded rods must be supported
by a rigid structure and should not
extend more than 2' (0.6m). If the
length of the rods exceed 2' (from
the support structure to the lift's
top mounting holes), cross bracing
should be installed between the
rods to increase the stability of the
installation.

Figure 3.

CORRECT POSITION OF THE LIFT IN THE FALSE CEILING:

-Determine the overall height of the lift with plasma screen and any optional accessories in a closed
position.
- Verify the vertical ceiling space available in the false ceiling. The height of the supporting structure is
calculated by deducting the overall height of the equipment from the vertical ceiling space available.
Note: Position the lift at correct height to have the ceiling closure "flush" with ceiling framework.
Caution: DO NOT ALLOW the front threaded rods to extend below the lift's top frame (in
the plasma screen area).

Figure 4 (Correct Position of the lift in the ceiling).