28 --

MI00/10056 rev.1--05/2001

5.1

Electrical connections

WARNING!

All electrical connections must

be made by a qualified electrician

and meet local electrical code standards

Before attempting to connect the mains supply, the reserve/bypass supply or the load, ensure that all supplies,
including the battery, are isolated and that all the equipment switches are in their »OFF» position.
Open UPS front access panel and remove internal panel over main switches and terminal blocks.

NOTES: 1) In accordance with para. 12.7 of UL 1778, the installation must be performed by a qualified

electrician. The terminals require the use of the proper crimp tools and terminals in order to
perform an installation in accordance with the National Electrical Code (NEC).
The recommended crimp tools, terminals and torque are shown in the followings tables:

2)Use Copper Conductors Only

Table of T& B’s cat.no.s for terminals and crimp tools