6 7.3.3 results of pv test – Furuno FELCOM 16 User Manual

Page 156

Advertising
background image

7. MAINTENANCE, TROUBLESHOOTING

7-6

7.3.3

Results of PV test

1. At the standby display, press the [F7] key to display the Options menu.
2. Press the [7] key to display the Test menu.
3. Press the [2] key to display the results of the PV test.

1. Login
2. Logout
3. Abort
4. Select NCS
5. Ocean Region
6. Test

Options

1. PV Test
2. PV Test Result
3. Self Test
4. Distress Alarm Button Test

Test

Test Date & Time

Attempts
BBER
Shore-to-Ship Attempts
Ship-to Shore Attempts
Distress Alert
Signal strength

Overall Result

02-02-25 01:58 (UTC)

First attempt
Pass
First attempt
First attempt
Pass (Test OK)
Pass (Greater than Std level + 10dB)

Pass (Applicable tests pass)

Ctrl+P: Print ESC: Quit

PV Test Result

Sample PV test results

4. To return to the standby display, press any key.

Interpreting the PV test results display

Test Date & Time:

Date and time of test

Attempts:

Number of times the PV test was conducted.

BBER:

Bulletin Board Error Rate (%). “Pass” appears for no
error.

Shore-to-Ship Attempts: Number of tests initiated by LES.
Ship-to-Shore Attempts: Number of tests initiated by MES.
Distress Alert:

“Pass (Test OK)” appears for successful testing.

Signal Strength:

“Pass” appears if signal strength is greater than
standard level.

Overall Result:

“Pass” appears for satisfactory completion of the
test.