Pre-Start-Up Checklist

o

Disconnect and lock-out all power switches.

o

Remove any foreign objects that are located in the

energy recovery unit.

o

Check all fasteners, set-screws, and locking collars

on the fans, bearings, drives, motor bases and
accessories for tightness.

o

Rotate the fan wheels and energy recovery wheels

by hand and ensure no parts are rubbing.

o

Check the fan belt drives for proper alignment and

tension.

o

Filters can load up with dirt during building

construction. Replace any dirty pleated filters and
clean the aluminum mesh filters in the intake hood.

o

Verify that non-motorized dampers open and close

properly.

o

Check the tightness of all factory wiring

connections.

o

Verify control wire gauge.

o

Verify diameter seal settings on the energy recovery

wheel.

o

Verify proper drain trap installation.

o

Check condensing fans for any damage or

misalignment. Spin the blades and make sure they
don’t contact any parts and are free turning without
any resistance.

o

Look over the piping system. Inspect for oil at all

tubing connections. Oil typically highlights a leak in
the system.

o

Inspect all coils within the unit. Fins may get

damaged in transit or during construction. Carefully
straighten fins with a fin comb.

o

If there is an indirect gas-fired furnace in this unit,

refer to the maual provided with this unit for Pre-
Start-Up information.

o

This unit contains a crankcase heater for each

compressor which needs power supplied to it
24 hours prior to start-up. If start-up is scheduled in
24 hours, unlock the disconnect power and energize
unit.

SPECIAL TOOLS REQUIRED

• Voltage Meter (with wire probes)
• Amperage Meter
• Pressure Gauges – (refrigerant)
• Tachometer
• Thermometer
• Incline manometer or equivalent

Start-Up Procedure

The unit will be in operational mode during start-up. Use
necessary precautions to avoid injury. All data must be
collected while the unit is running. In order to measure
volts and amps, the control center door must be open,
and the unit energized using a crescent wrench to turn
the disconnect handle.

o

Make sure Pre-Start-Up checklist is complete.

o

Jumper R to G, R to Y1, and R to Y2 (if applicable)

on the control board.

o

Turn the disconnect on. After 3 minutes

compressors will come on. Make sure all fans and
compressors are rotating the correct direction.

o

Allow the unit to run until the refrigerant system

stabilizes. Approximately 1-2 minutes.

Voltage Imbalance

In a 3-phase system, excessive voltage imbalance
between phases will cause motors to overheat and
eventually fail. Maximum allowable imbalance is 2%.
To determine voltage imbalance, use recorded voltage
measurements in this formula.
Key:

V1, V2, V3 = line voltages as measured

VA (average) = (V1 + V2 + V3) / 3

VD = Line voltage (V1, V2 or V3) that

deviates farthest from average (VA)

Formula:

% Voltage Imbalance = [100 x (VA-VD)] /VA