Piping

15

5.3

Connection Methods and Points

Refer to site specific drawings for general locations of the piping connections. For Liebert XDH con-

nection locations, refer also to Figure 16.
The assembly and connection means used for piping in the Liebert XD system are the same as those

used in conventional refrigeration systems. Observe all standard practices during installation and

startup to prevent damage and contamination.
Supply piping connection is 1/2" OD copper pipe, and return piping connection is 7/8" OD copper. Both

supply and return fittings may be supplied with optional one-shot connections. These fittings contain

pressurized R-134a refrigerant inside the Liebert XDH.
The Liebert XDH has supply and return piping access on the top of each module.

Figure 15 Hard pipe connection diagram

Rear of

Liebert XDH

Copper Tubing
Total length of each
line from Liebert XDH
to Main; not to exceed
72" (1829 mm)

Top of

Liebert XDH

Recommended Arc

Supply Main
(seen from end )
1-1/8" O.D.
or 1-3/8" O.D.

1/2” Refrigerant -Grade
Full-Port Ball Valve
Field-Supplied and
Field- Installed

Return Main
(seen from end )
2-1/8" O.D.
or 2-5/8" O.D.

Acceptable Arc

7/8” Refrigerant-Grade
Full-Port Ball Valve
Field-Supplied and
Field-Installed

Supply
to Cooling
Module

Return from
Cooling Module

Refer to Table 2 for details.