To make PV Array #1 and GT100E #1 connections:

1. Route the PV Array #1 cables through the access panel and connect

the cables to PV ARRAY #1 PV(+) and PV(-) terminals, see Figure 2-
5.

2. Route the GT100E #1 cables through the access panel and connect the

cables to GT100E #1 PV(+) UNIT and PV(-) terminals, see Figure 2-
5.

3. Route the PV Array #1 ground cable through the access panel and

connect the cable to PV ARRAY #1 GND terminal, see Figure 2-5.

Figure 2-5 PV Array #1 and GT100E #1 Connections

Combiner Box
PV ARRAY #1
GND Terminal

Combiner Box
PV ARRAY #1
PV (+) Terminal

Combiner Box
PV ARRAY #1
PV (-) Terminal

Combiner Box
GT100E #1
PV (+) Terminal

Combiner Box
GT100E #1
PV (-) Terminal