Fan and Heater

FAN PARTS

Figure 4: The HF-7318 control board.

For Units Using

HF-7318 Control Board

2 Deluxe heaters may be connected to one grain

drying system and wired so they cycle together.

One of the heaters should have a thermostat

connected to it as per the installation instructions.

That heater will be referred to as the master. The

other heater (without the thermostat) will be

referred to as the slave.

Installation For

Standard Units

1. Install relay base (TD-100283) in master

heater control box.

2. Connect wire between term 6 on circuit board

and terminals 14 on relay base in master

heater.

3. Connect wire between term 13 on relay base

and terminals 8 on circuit board in master

heater.

4. Run 2 wires (18 gage) between master and

slave heaters.

5. Connect wires to terminal 5 and 9 (points A

and B) on relay base in master heater.

6. Connect wire from terminal 9 in master to

terminal 14 (point F) in slave unit.

7. Connect wire from terminal 5 in master to

terminal 15 (point E) in slae unit.

8. Install relay (TD-100282) in relay base.

Additional Steps For

Hi-Lo Units

1. Run 2 wires (18 gage) between master and slave

unit.

2. Connect wires to terminals 21 and 22 (points C

and D) on circuit board in main heater.

3. Connect wire from terminal 21 in master to

terminal 12 (point H) in slave unit.

4. Connect wire from terminal 22 in master to

terminal 13 (point G) in slave unit.

5. Install relay (TD-100282) in relay base.