6. Operation
36
PNEG-1049 10"-12" Commercial Bin Sweep Augers
Figure 6L
23. Check the sweep carrier wheel assembly. If necessary, adjust the height so that the sweep arm
assembly is close to the floor, but will not contact the floor, intermediate well top flanges or the
floor screws.
24. Exit the grain bin.
25. Make sure everyone is outside of the bin and clear of the equipment.
26. Start the unload auger and then the bin sweep. Shortly, the swept pile will have been removed by the
bin sweep.
27. Disconnect and lock out all power to the bin sweep and unload auger.
28. Repeat
, moving the grain into a smaller circular pile, as shown in
.
29. Repeat
.
30. Exit the grain bin.
31. Make sure everyone is outside of the bin and clear of the equipment.
32. Start the unload auger and then the bin sweep. Shortly, the swept pile will have been removed by the
bin sweep.
Cleaned area
Remaining grain
Bin wall
Bin sweep
Bin wells