6.7.1 Outfitting the hoist

• Install the power supply. Refer to the section “Connecting the to mains network”.
• Adjust the limit switch for hoisting. Refer to the section “Adjusting hoisting limit switch”.

• Carry out the commissioning inspection and complete the commissioning log. Refer to the section

“Commissioning”.


6.8 Installing the hoist, machinery hoist

c_hmv3b

• Remove the temporary transport supports. Take the hoist out of the packing and move it to the

installation site.

• Check that the fixing holes in the site of location match the fixing holes (1) in the hoist.

• Change electric cubicle position if needed.

#

All fixing directions A, B, C and D are possible. Move the fixing parts (2) to correct fixing corners.

• Lift the hoist into position. Fasten the fixing screws.

• Instal rope reeving.

!

Instal rope direction(s) according to manufacturer’s instruction. Be in contact with
authorised hoist service.


6.8.1 Outfitting the hoist

• Install the power supply. Refer to the section “Connecting the to mains network”.
• Adjust the limit switch for hoisting. Refer to the section “Adjusting hoisting limit switch”.

• Carry out the commissioning inspection and complete the commissioning log. Refer to the section

“Commissioning”.