The CFR is designed so that battery backup time can be greatly

extended simply by plugging the EBP 24 External Battery Pack into the back
of the UPS. Battery packs are completely self-contained.

*Battery run times are calculated at typical load (80%) and represent the total time of the CFR internal

batteries and EBP battery pack.

1. Switch the CFR's BATTERY circuit breaker OFF.
2. Locate the EXTERNAL battery connector on the rear panel of the UPS

and remove the Phillips screw #1 and loosen Phillips screw #2.

3. Slide the cover plate to the left and insert the battery pack’s connector

into the UPS. Secure the connector to the UPS using the Phillips screw
#1.

4. Switch the EBP and CFR “BATTERY” breakers ON and test the unit

for proper operation.

18

3. INSTALLATION

Note: Battery Pack
can be installed along
side, or underneath
the CFR UPS.

Figure 7

CFR 600 and EBP External Battery Pack

3.3 External Battery Pack

BATTERY

Circuit Breaker

Unit

Rating

Voltage

Run Time*

CFR 600

CFR 600XT CFR 1000

EBP 24A

17 Ah

24 VDC

0.66 hrs

1 hrs

0.5 hrs

EBP 24C

66 Ah

24 VDC

3.75 hrs

4.3 hrs

2.1 hrs

EBP 24E

176 Ah

24 VDC

8.5 hrs

9.0 hrs

5.0 hrs