Brooks Instrument MT3809E User Manual

Page 59

Advertising
background image

4-5

Section 4 Maintenance

Models MT 3809 and 3819

Installation and Operation Manual

X-VA-MT3809-3819-eng
Part Number: 541B049AHG
September, 2008

the float assembly up and out the top/outlet side.

5.

Reassemble by inserting the float assembly into the top of the meter.
Replace the guide vane (#3) and secure the float assembly by
tightening the inlet and outlet screws (#2). Reinstall and secure the inlet
fitting (#4).

c. Size 8 (1/2”) NPT Gas Service

1.

Remove the meter from the process line and lay the meter horizontal
on a table.

2.

Unscrew the outlet fitting (#4) at the top/outlet of the meter and remove
the gas damper.

3.

Unscrew the inlet/bottom fitting (#4) and slowly remove the float
assembly.

4.

To reassemble the meter, insert the float assembly into the inlet/bottom
of the meter. Secure the inlet/bottom fitting (#4). Replace the gas
damper and secure the outlet/top fitting (#4).

d. Sizes 10 (1"), 12 (1 1/2"), 13 (2") NPT Gas Service

1.

Remove the meter from the process line and lay the meter horizontal
on a table.

2.

Remove the top/outlet screw (#5).

3.

Loosen the float assembly by holding the damper in place with a pin
(1/8” diameter) in the top while loosening the inlet/bottom fitting. Gently
push the float assembly out through the inlet/bottom.

4.

To clean the gas damper, unscrew the cylinder head (#6). Then remove
the bolt (#7) and take out the small piston carefully so as to not damage
the critical surfaces.

5.

Reassemble the meter by inserting the float assembly with damper into
the inlet/bottom of the meter. Secure the inlet/bottom screw by holding