SIGN OFF WHEN PRE-START CHECKS ARE COMPLETED: ____________________________
FIRST TIME START-UP CHECK LIST
INNOVATOR PRO
ACTIVITIES MUST BE DONE IN THE SEQUENCE SHOWN, AND MUST BE TICKED
OFF AS COMPLETED. THIS SEQUENCE FOLLOWS ON FROM “PRE-START
CHECKLIST INNOVATOR PRO”
ACTIVITY
NO.
ACTIVITY
TICK WHEN
COMPLETED
Priority
Put on Respirator as specified for spray painting, Protective
Clothing, Eye Protection, and PVC Gloves
1
Turn the pump regulator to zero
2
Adjust the catalyst percentage required with the slide arm Knob.
3
With all the material containers properly filled. Press the
Recirculation Button on the control panel.
4
Slowly increase the pump regulator so that the pump strokes
slowly and evenly.
5
Allow the pump to recirculate until the flow of Resin and Catalyst
back to there respective containers is free of bubbles.
6
Press the Stop button to take the unit out of recirculation mode
7
Test the catalyst and resin to the Injection head – Place a
suitable container under the injection head and press the Inject
button. After 4 or 5 strokes press the Stop button.
8
Check that the material properly cures
9
Properly dispose of the catalyst and resin.
10
Flush the Injection head as necessary into the appropriate
container.
ABNORMAL CONDITIONS OBSERVED AND CORRECTED
Abnormal Condition
a
a
a
a when
corrected
OPERATORS NAME
________________________________
DATE:
____________
SIGN OFF WHEN START UP CHECKS ARE COMPLETED:
_______________________