Daily shut down checklist innovator pro, Activity – Magnum Venus Plastech INNOVATOR PRO 5000 (8003) User Manual

Page 37

Advertising
background image

MAGNUM VENUS PLASTECH

Innovator Pro Manual

37




DAILY SHUT DOWN CHECKLIST

INNOVATOR PRO

ACTIVITIES MUST BE DONE IN THE SEQUENCE SHOWN, AND MUST BE TICKED
OFF AS COMPLETED. THIS SEQUENCE FOLLOWS ON FROM “DAILY START UP
CHECKLIST”



ACTIVITY

NO.

ACTIVITY

TICK WHEN
COMPLETED

Priority

Put on Respirator as specified for spray painting, Protective
Clothing, Eye Protection, and PVC Gloves

1

Press the Stop button to Close the injection head, TAS (Turbo
Autosprue) or pinch injection hose to close the mould

2

Press the Reset button on the Counter to reset the counter.

3

Flush the injection head and hose or TAS (Turbo Autosprue)

4

Disconnect the injection hose or TAS from the injection head.

5

Turn off the main air slide valve at the back of the unit.



ABNORMAL CONDITIONS OBSERVED AND CORRECTED

Abnormal Condition

a

a

a

a when
corrected



OPERATORS NAME

__________________________________

DATE:

_______________

SIGN OFF WHEN SHUT DOWN CHECKS ARE COMPLETED:

__________________________




Advertising
This manual is related to the following products: