INSTALLATION

VMPW-IOM-2012-1001

SECTION 2

2-16

Air Flow
Safety Switch

U.L. Approved
Induced Draft Fan

Side Wall

Vent

Termination

(By Others)

Side Wall Vent
(By Others)

FIGURE 3 - TYPICAL SIDEWALL VENTING

3. The draft fan should be located as close to the fl ue

outlet as possible.

4. Draft regulation suffi

cient to lower the draft to between

-0.02 to -0.04 “ wc may be required. The draft regulator
must be between the boiler and the fan.

5. The draft fan shall have an air fl ow proving switch wired

in series with the boiler air safety switch.

6. The sidewall vent total length from boiler exhaust to

termination shall not exceed 35 feet (10.6 m) with 4
elbows maximum.

Testing

Upon completion of the installation, perform the following
testing:

1. A pneumatic test of water piping not exceeding 15

psig.

2. Leak tests at all welds and joints to ensure that the

system is free from leaks.