Section 3: Scale Installation

3.1. INTRODUCTION

The service information contained in this manual is restricted for use by authorized,
qualified service personnel only. Under no circumstances are unauthorized
personnel to disassemble or otherwise tamper with this, or any related equipment.

3.2. PREPARATION FOR INSTALLATION

1.

Tools, equipment, and materials required:

a.

Hydraulic jacks -- Use hydraulic jacks that have sufficient capacity plus (+)
a safety factor for the size of the vessels you are installing the Omnicells.

b.

Blocking material to support lifted vessel.

c.

Determination of how the scale system will be calibrated.

Calibration weights (Only application method for NTEP system)

i.

Get calibration weights on site

ii.

Dolly, or other method, for moving weights

iii.

Means for lifting calibration weights (chains, Come-Along winch, etc.)

iv.

Lifting point on vessel for supporting calibration weights

Substitution – Product measured by other device (scale, flow meter,
etc.) then used as the calibration weight.

i.

Schedule product to arrive when needed

ii.

Determine how product will be put into, and removed, from vessel

MilliVolt calibration with Intalogix Technology

i.

Check to make sure the correct equipment was ordered (Q
Series instrument and Quad Multiplexer Board or Flash
Instrument, Smart Sectional Controller and Pit Power Supply)

ii.

Load cell calibration sheets

NO ARC WELDING is permitted near Omnicell
installations. Severe damage to the load cells can
occur. If welding is required, remove the load cell or
remove the unit and install blocks.