3.4.5. Loading a Test Plan from the EZCT S2’s Flash EEPROM
To use a test plan for running a test, it must first be loaded into the working memory. To load a
test plan from the EZCT S2’s Flash EEPROM into the working memory:
a. Start from the “START-UP” menu:
Press the
[3]
key (TEST PLANS).
b. The following screen will be displayed:
Press the
[1]
key (LOAD TEST PLAN).
c. The following screen will be displayed:
Type the test plan number that you would like to load and press the
[ENTER]
key. If
you do not know the test plan number, you can print a test plan directory using the
instructions in section 3.4.2.
d. The following screen will be displayed:
Press any key to return to the “START-UP” menu.
TEST PLAN LOADED!
LOAD TEST PLAN
NUMBER:
1.
LOAD TEST PLAN
2.
UNLOAD TEST PLAN
3.
PLAN DIRECTORY
4.
NEXT PAGE
1.
RUN TEST 09/24/09
2.
SETUP 08:20:19
3.
TEST PLANS
4.
DIAGNOSTIC