5.3.3. Checking phase sequence and phase concordance with a lead

WARNING

While measuring, the instrument must be held in the operator’s hand.

Press key F1 (Mod) to open the drop-down menu shown on the
screen to the side. At each subsequent pressure of key F1
(Mod), the cursor will scroll through the available items. Select
Ph Seq” and press key F4 (OK) to confirm the selected item.

Mod

Par Ok

A C < 1 0 . 0 H z


- - - -

V

19/01-17:00:00

5.3.3.1. Verification of Phase Sequence.

Fig. 7: verification of phase sequence


1. The instrument shows the screen here to the side, and waits

for the detection of phase L1.

2. Insert the red cable into input terminal V

Ω and connect the

red lead to phase L1 (Fig. 7).