1. Create a loop on the uphole end of the cable and loosely bind it with one zip tie.

2. Place the metal loop inside the cable loop. Push the zip tie up to form a tight band

around the metal loop. Tighten the zip tie.

3. Place the second zip tie directly below the first and tighten.

4. Place the third zip tie about 2.5 cm (1 in.) below the first two ties. Place the fourth zip

tie snugly against the third.

5. Hand tighten the zip ties. Do not over tighten.

6. Clip the excess tie material from the unit.

7. Deploy from a well dock or other secure location.