3.7.3 Process connections
Before mounting of the device, please check the correct position of the high (H) and low (L)
pressure side. You can see the designations (H / L) underneath the measuring cell acc. to the
figure.
The process connections of the differential pressure transmitter are usually 1/4-18 NPT (female)
at a distance of 54 mm / 2.13". Through optional oval flange adapters the connections 1/2-14
NPT (female) are also selectable.
Figure 3-2: Installation in double chamber housing
1 Insert the display and adjustment module into the housing
2 Turn the display and adjustment module clockwise
3 Mounting on top
4 Mounting at side
Figure 3-3: Process connection of the differential pressure transmitter
1 High-pressure side
2 Low-pressure side