OPERATIONAL STARTUP

The following practices should be observed when installing and starting the meter

make sure that fluid flOw has been shut Off and pressure in the line released befOre attempting tO

install the meter in an existing system.

1 After meter installation, close the isolation valves and open the bypass valve Flow liquid through the bypass valve for

sufficient time to eliminate any air or gas in the flow line

damage can be caused by striking an empty meter with a high velOcity flOw stream.

2 Open upstream isolating valve slowly to eliminate hydraulic shock while charging the meter with the liquid Open the

valve to full open

3 Open downstream isolating valve to permit operation
4 Close the bypass valve to a full closed position
5 Adjust the downstream valve to provide the required flow rate through the meter

NOTE:

N

Downstream valve may be used as a control valve

DIMENSIONS

A

C

B

A

B

C

8.80 in. (223.5 mm)

8.00 in. (203.2 mm)

6.10 in. (154.9 mm)

User Manual

Page 7

September 2013

Advertising