Installing the Meter

1 Install the meter in the pipeline making sure that the flow arrow on the meter housing is in proper relation to the

direction of liquid flow It is also recommended that ten pipe diameters upstream and five pipe diameters downstream of

straight pipe be incorporated with no obstructions If this is not possible, please contact factory to review acceptability

of installation

2 Install and tighten the flange connection bolts
3 To relieve possible strain on the piping due to the weight of 4" and 6" turbo meters, it is recommended that consideration

be given to installation of a meter support under the meter housing

U

Figure 1: Recommended Meter Installation

Performance Checks

Complete the following checks to ensure that the meter is properly installed and operational
1 Slowly open the upstream valve to apply liquid pressure to the meter and check the flange connections for possible leaks

Retighten the flange bolts as required

2 Perform a functional test of the turbo meter using the adjustment and calibration procedure in this manual

Bypass

(Permanent

or

Temporary)

Upstream

Valve (open)

Minimum of 5

diameters of

straight pipe

Minimum of 2

pipe diameters

downstream of

Turbo meter

Test tee

Downstream

Shutoff

valve

Service

saddle

Coupling

adapter

Badger Meter plate

strainer and Turbo meter

Industrial Turbo Meters, Sizes 2" through 6"

Page 6

November 2013