150kW InfraStruXure System—Installation and Start-Up
31
Route Data Cables to the InfraStruXure
Manager Hub (or Switch)
1. Connect a Cat-5 network cable (provided) to the network or 10 Base-T ports on your APC
InfraStruXure devices. The following devices need to be connected:
2. Route the connected Cat-5 network cables through the data cable troughs to the InfraStruXure
Manager Hub (or Switch).
3. Connect each device’s network cable to any available station port in the InfraStruXure Manager
Hub (or Switch). Station ports are those with an x after the number (e.g., 2x).
Automatic Transfer Switch
Rack PDU
Environmental Monitoring Unit
InfraStruXure PDU