Installing the mcs 5042 unit – HP Modular Cooling System User Manual

Page 10

Advertising
background image

Installation 10

Installing the MCS 5042 unit

WARNING:

The MCS 5042 unit and rack are shipped together on a heavy duty shock pallet

weighing approximately 1600 kg (3600 lb). HP recommends hiring professional movers to move
the heavy duty shock pallet, remove the MCS 5042 unit and rack from the pallet, and move the

MCS 5042 unit and rack to the final location.

CAUTION:

Contaminated water might cause decreased cooling capacity or disruption in

service. The water flowing into the MCS 5042 unit must meet the guidelines stated in the HP

mc-Series 5042 Rack Site Preparation Guide. The HP mc-Series 5042 Rack warranty does not

cover damage caused by contaminated water.

IMPORTANT:

Because the MCS 5042 unit consumes a large quantity of water, HP recommends

that you do not operate the MCS 5042 unit from a public water system such as one that supplies
drinking water. For water conservation purposes, to cool the MCS 5042 unit, use only recycled

water systems.

IMPORTANT:

Before you begin the installation process, review the HP mc-Series 5042 Rack Site

Preparation Guide.

1.

Install the HP mc-Series 5042 Hook Up Kit.

2.

Read the unpacking instructions on the MCS 5042 packaging material.

3.

Using four or more people, remove the MCS 5042 unit and rack from the pallet.

4.

Roll the MCS 5042 unit and rack to the final location.

WARNING:

To avoid tipping the MCS 5042 unit over, make sure the leveling feet are lowered

when the MCS 5042 is equipped, serviced, and operated.

5.

To adjust the leveling feet and level the MCS 5042 unit, use a bubble level.