Installing the pci express mezzanine options – HP ProLiant DL580 G3 Server User Manual
Page 86

86
HP ProLiant DL580 Generation 3 Server User Guide
14.
Install the basket.
15.
Install the PCI-X Hot Plug expansion boards. If the server is powered off,
use non-hot-plug procedures ("Installing non-hot-plug expansion boards" on
page
) to install the expansion boards. If the server is running, install PCI-
X Hot Plug expansion boards using hot-plug procedures ("Installing hot plug
expansion boards" on page
16.
Reinstall any expansion boards removed to install the PCI-X Hot Plug
Mezzanine Option.
17.
Place the expansion slot covers over any remaining empty expansion slots,
and close the latches.
CAUTION: To prevent improper cooling and thermal damage, do
not operate the server unless all expansion slots have either an
expansion slot cover or an expansion board installed.
18.
Replace the access panel ("Removing the access panel" on page
19.
Slide the server back into the rack.
20.
Power up the server ("Powering up the server" on page
Installing the PCI Express mezzanine options
1.
Power down the server ("Powering down the server" on page