INSTALLATION INSTRUCTIONS

for Vinyl Patio Doors with Integral Nailing Fin (JII006)

4

INSTALL SILL PAN

1. Set the sill pan in

the rough opening,
aligning the front
edge (for continuous
slab) or folded down
edge (for step down)
with the exterior of
the rough opening.

2. Mark a line across

the front and back of
the sill pan.

3. Apply three 3/8"

beads of sealant
between the lines.

4. Place the sill pan in

the rough opening.
Firmly press the sill
pan into the sealant
with a J-roller.

Sealant

3. Cut a piece of self-

adhesive flashing
the length of the sill
and apply over the
entire sill pan. For
step down landings,
fold flashing down
as shown. For
continuous slabs,
trim flush with
rough opening.

4. Cut two pieces of

self-adhesive flashing
9" wide by the sill
pan width + 3" long.
a. For continuous

slab landings
only, cut out the
inside corner.

b. Adhere the pieces

of flashing to the
inside corners.
Stretch flashing
as needed to
cover corners and
lay flat.

5. Smooth gaps or

bubbles beneath
self-adhesive flashing
with a J-roller
(remove and replace
if necessary).

6. Seal back corners of

sill pan with sealant.

7. For step-down

landings only, cut
plastic drain screen
to length of sill + 2",
center, and staple
1/2" below sill edge.

PREPARE BUILDING WRAP

Note!

Check with

the building wrap
manufacturer to verify
the following steps will
not void their product
warranty.
1. Trim building wrap

flush with the
rough opening.

2. At the head, cut

building wrap at
45° and tape up
as shown.

3. Trim the sides of the

building wrap sufficiently to allow the nailing fin to be mounted
against the sheathing.

INSTALL JOBSITE FABRICATED SILL PAN

Note!

The rest of the steps in this section only apply to a job site

fabricated sill pan. If installing a sill pan that you have purchased,
follow manufacturer's instructions for installation and skip to section 5,
“INSTALL PATIO DOOR.”
1. If installing a metal

sill pan on concrete,
cut a piece of self-
adhesive flashing
the length of the sill
pan and adhere it to
the entire bottom
surface where the
pan will sit on the
concrete.

2. If fasteners are

required through
the sill, apply
spray adhesive/
primer to the sill pan and surrounding area. Follow spray adhesive
manufacturers' instructions for application methods.

Sill pan

width

3"

9"

Discard

(for

continuous

slab only)

Continuous Slab

Landing

Sill pan

width

6"

3"

Step-Down

Landing

Sill pan

width

6"

3"

Sealant

45˚

1/2"

1"

Spray Adhesive

6"

6"

INSTALL SILL PAN - CONTINUED

PREPARE STUD-FRAMED WALL